by Paul Kiefer / Wisconsin Watch, Wisconsin Watch
July 30, 2026
We Energies reassured shareholders on Wednesday that Oracle’s ongoing dispute with state regulators over new credit rating requirements for data center operators poses no threat to the planned hyperscale data center in Port Washington.
WEC Energy Group CEO Scott Lauber, head of We Energies’ parent company, told investors during a quarterly earnings call that the Port Washington facility remains on track to come online as soon as late 2027. In a “worst-case scenario” in which Oracle backs out of the project, “there are a lot of opportunities for that site,” Lauber said, “but at this point, I have no indication that’s the case.”
Wisconsin’s Public Service Commission (PSC) in April approved a rate structure for We Energies’ “very large customers” that requires operators like Oracle to pay for the construction of new power plants needed to meet data center energy needs. But constructing a new plant can cost hundreds of millions of dollars, and any unpaid debts tied to the plants could fall on We Energies’ other customers if a data center operator becomes insolvent.
To shield ratepayers from a potential cost shift, the PSC set a AAA- credit rating threshold for data center operators seeking electric service from We Energies. Companies below the threshold must post steep collateral, either in cash or lines of credit, as a backstop.
That requirement could cost Oracle, the co-developer of the Port Washington data center campus alongside OpenAI and Vantage, over $100 million per year in financial security payments. The company held a BBB credit rating when the PSC approved the credit rating standards, largely because of its aggressive borrowing to finance artificial intelligence ventures and risky business relationship with OpenAI. S&P Global Ratings, one of the “Big Three” credit rating agencies responsible for assessing creditworthiness of government and corporate debt, lowered Oracle’s rating to a BBB- on July 9 — the bottom edge of the agency’s “investment-grade” tier. If the company’s credit rating falls further, Lauber said, “we already have all the collateral we need.”
We Energies asked the PSC to reconsider the rule last month, arguing that the added cost could dissuade other companies from operating in Wisconsin. “If the Commission does not reopen its decision on this issue, the implications for Wisconsin would be significant and limit the ability of numerous investment-grade companies to invest in Wisconsin,” the utility’s attorneys wrote in their request. The PSC declined We Energies’ request earlier this month.
Lauber sounded more optimistic about the credit rating requirements on Wednesday. “I don’t think the collateral will be an issue long term,” he said, noting that ratings agencies reacted positively to the credit rating threshold.
We Energies is currently in talks with at least two other data center operators interested in setting up Wisconsin operations, albeit at far smaller scales than Oracle or Microsoft, which operates a new data center campus in Mount Pleasant. Lauber told shareholders that the credit rating requirements pose no obstacle to those prospective customers.
Oracle, however, sued the PSC in Ozaukee County Circuit Court last month, asking a judge to “set aside, reverse and remand” the credit rating requirements. The tech giant argues the commission acted outside of its authority in approving the rule and that the AAA- bar isn’t “needed to prevent harm” to We Energies’ other customers.
We Energies is an interested party in that lawsuit, but it did not join Oracle as a plaintiff.
This <a target=”_blank” href=”https://wisconsinwatch.org/2026/07/wisconsin-we-energies-oracle-dispute-port-washington-data-center-on-schedule-legal-challenge-credit-rating/”>article</a> first appeared on <a target=”_blank” href=”https://wisconsinwatch.org”>Wisconsin Watch</a> and is republished here under a <a target=”_blank” href=”https://creativecommons.org/licenses/by-nd/4.0/”>Creative Commons Attribution-NoDerivatives 4.0 International License</a>.<img src=”https://i0.wp.com/wisconsinwatch.org/wp-content/uploads/2021/02/cropped-WCIJ_IconOnly_FullColor_RGB-1.png?fit=150%2C150&quality=100&ssl=1″ style=”width:1em;height:1em;margin-left:10px;”>
<img id=”republication-tracker-tool-source” src=”https://wisconsinwatch.org/?republication-pixel=true&post=1319364&ga4=G-D2S69Y9TDB” style=”width:1px;height:1px;”><script> PARSELY = { autotrack: false, onload: function() { PARSELY.beacon.trackPageView({ url: “https://wisconsinwatch.org/2026/07/wisconsin-we-energies-oracle-dispute-port-washington-data-center-on-schedule-legal-challenge-credit-rating/”, urlref: window.location.href }); } } </script> <script id=”parsely-cfg” src=”//cdn.parsely.com/keys/wisconsinwatch.org/p.js”></script>