    • A Montana Community Rallies to Save Its Beloved Ski Hill
    • 18-km pipeline installation and platform upgrades boost Gulf of Suez field
    • Listen to 911 Calls From Inside an Immigration Detention Center — ProPublica
    • In Wisconsin Rapids, data center objections include developers’ Russian connections
    • To End Global Hunger, Invest in Rural Communities by Esther Ngumbi
    • No, Covid stats don’t indicate it’s ‘officially back’ – Full Fact
    • Uganda’s King of Tooro, once world’s youngest reigning monarch, dies at 34
    • Why These Giant Storage Tanks Increasingly Hold Very Little Oil
    • About
      • Our Team
      • Editorial Policy
      • Editorial Independence
      • International Support
    • Trust & Standards
      • AI Usage Policy
      • Conflict of Interest Policy
      • Corrections Policy
      • Ethics Policy
      • Fact-Checking Policy
      • Source Protection
    • Get Involved
      • Guide for Sources
      • Support Independent Journalism
    • Legal
      • Cookie Policy
      • Privacy Policy
      • Terms of Use
    Facebook X (Twitter) Instagram
    NCIJ Network NCIJ Network
    Friday, August 28
    • Home
    • World
    • Ai
    • Business
    • Politics
    • Health
    • Crypto
    • Science
    • Technology
    • Cybersecurity
    • Defense & Security
    • Economy
    • Energy
    • Europe
    • More
      • Fact Check
      • Investigations
      • Opinion & Analysis
      • Environment
    NCIJ Network NCIJ Network
    Home»Investigations

    In Wisconsin Rapids, data center objections include developers’ Russian connections

    NCIJ NETWNCIJ NETWORKBy NCIJ NETWNCIJ NETWORKAugust 28, 2026 Investigations No Comments8 Mins Read
    Share
    Facebook Twitter LinkedIn Pinterest Email

    Reading Time: 5 minutes

    No matter where in the U.S. an artificial intelligence data center is proposed, communities express the same worries.

    Water scarcity and contamination, electricity rates and reliability, air pollution, noise.

    Residents are voicing those same concerns 100 miles north of Madison in Wisconsin Rapids, where developers want to replace a former paper mill with a 210-acre data center. 

    But there’s another worry in Rapids that makes the situation different from other Wisconsin communities where data centers have been proposed:

    Russians.

    “I hear it from other people; people bring it up very often,” data center opponent Mary Olson said.

    Ruslan Zinurov, the man who first proposed the data center, was born in Russia.

    Anton Voronkin, who has since taken over the project, was born and educated in Russia and worked there for years.

    Marissa Johnson, a leader of a group fighting the data center, said that while residents have environmental concerns, the Russian ties are “a sticking point for people.” Some residents don’t say so publicly, out of fear of being perceived as xenophobic, but they worry about the developers’ past business practices, she said.

    A person wearing sunglasses holds a printed map while standing across a road from an industrial area.
    Marissa Johnson, a member of South Wood County Neighbors for Responsible Development in Wisconsin Rapids, Wis., holds a zoning proposal by industrial real estate development firm PNK Group detailing a plan to develop a large-scale data center campus on the site of the former Wisconsin Rapids paper mill. (Drake White-Bergey for Wisconsin Watch)

    The questions aren’t limited to whispering.

    At public meetings, residents mostly express common fears: How much water will the data center use? Will my electricity rates go up? How can we know it won’t cause air and noise pollution? 

    One woman urged city officials to “just do the right damn thing” and find any way to block data centers.

    But at a city meeting in July, a woman said a “Russian national” had applied to the city for a permit for the data center.

    In August, at a meeting organized by the team proposing the data center, one audience member drew applause from the audience when he said to Voronkin: 

    “We like to know who’s running this operation. And from what I understand, you, sir, are not an American citizen; you’re Russian. Am I right or wrong?” 

    Voronkin’s reply didn’t seem to satisfy the crowd. “I have worked in many countries overseas,” he said.

    Russian born, Green Bay ties

    The first record of the data center proposal is an email sent Dec. 16 by Zinurov to Wisconsin Rapids city planner Kyle Kearns. He wrote that he was looking to acquire a site in the city of 19,000 to convert into a data center. 

    The location turned out to be part of a former paper mill site near downtown and the Wisconsin River.

    Kearns replied the next day, writing: “It is exciting to hear about your interest!”

    By February, Zinurov had met with Kearns and Mayor Matt Zacher. He said in an email that he was working to acquire part of the mill site. He wondered if the city could help secure electricity and natural gas for the operation.

    The proposal didn’t make news until April, when the city planning commission announced a public hearing on Zinurov’s application for what is known as a conditional use permit.

    The 43-year-old Zinurov identified himself as being with California-based Performance Computing Holdings. In a 2020 article about a Zinurov-led investment in Ukraine, Zinurov told the Kyiv Post he was born in Russia, his wife is Ukrainian and he had been living in the U.S. more than 15 years.

    He also has Wisconsin ties.

    Zinurov’s cellphone number has a 920 area code, which covers Green Bay. According to his LinkedIn profile, he has a bachelor’s degree in business administration from the University of Wisconsin-Green Bay, plus a master’s degree in the same subject from the University of California, Berkeley.

    Zinurov’s profile also says he founded a company originally known as Consensus Technology Group. In a 2024 interview, he said that company operates data centers in North Dakota, South Dakota, Pennsylvania and Missouri. 

    According to news reports, Zinurov also partnered with Chinese tech company Bitmain to convert a former paper mill in Washington state into a cryptocurrency-mining business.

    Vinurov declined Wisconsin Watch’s requests for an interview, noting in a text that Voronkin has taken over the Wisconsin Rapids project. 

    Vinurov wrote that he “spent a good chunk of my life in Green Bay, so Wisconsin indeed has a special place in my heart. Go Pack.”

    New face of the project

    As Zinurov has worked behind the scenes, Voronkin, 42, has become the public face of the Rapids proposal.

    By early May, a week after Zinurov filed the permit application, city planner Kearns had turned to emailing with Voronkin instead. Kearns noted that Voronkin and one of his team members, former New York City Mayor Eric Adams, had made plans to visit Wisconsin Rapids.

    Adams’ background has also riled some residents. While mayor, he was indicted on federal conspiracy charges, which he denied. In April 2025, the charges were dismissed at the request of the U.S. Justice Department.

    Voronkin, who was born in Russia, says in his LinkedIn profile that he earned bachelor’s and master’s degrees in St. Petersburg, Russia. The profile says he worked in commercial development in Russia from 2009 to 2022, when he began development work on Neom, a $500 billion ​mega-project in Saudi Arabia.

    The nonprofit group Human Rights Watch reported in December 2024 that Neom workers suffered abuse, such as being paid less than they were promised. The same month, a Wall Street Journal investigation found Neom employees reported incidents of gang rape, suicide, attempted murder and drug dealing on the site. 

    In 2026, Voronkin became chief development officer, including for data centers, at PNK Group, a New York-based developer of industrial buildings. 

    A chain-link fence is next to piles of rocks and industrial materials. A sign on the fence reads "DANGER DO NOT ENTER WITHOUT AUTHORIZATION."
    The site of a former paper mill in Wisconsin Rapids, Wis., is photographed on Aug. 12, 2026. Industrial real estate development firm PNK Group proposed a plan to develop the site into a large-scale data center campus. (Drake White-Bergey for Wisconsin Watch)

    PNK began operations in Russia around 2003, according to the Scranton Times-Tribune in Pennsylvania, where PNK is proposing a data center. 

    Voronkin said at the August meeting in Wisconsin Rapids hosted by his team that PNK “withdrew the brand from Russia in 2024.”

    Data center opponent Mike Schmidt, a local attorney, said he doesn’t trust PNK because of Voronkin’s work with Neom and what Schmidt described as corruption allegations against PNK owner Andrey Sharkov.

    In two federal court lawsuits over business matters, Sharkov is accused of fraud in Pennsylvania and is the subject of a racketeer/corrupt organization lawsuit in Utah. Both cases are pending, and Sharkov has denied the allegations.

    “It’s not just that they’re Russian, it’s that they’re behaving in a corrupt fashion,” Schmidt said of Voronkin and Sharkov.

    Voronkin declined Wisconsin Watch requests for an interview. In messages, he wrote: 

    “I am not aware of such concern about my work for Neom. I am proud to be a part of the biggest development in the world and most likely in history. I wish more people had same level of ambitions and could think about the future same way as Neom. There are no corruption charges against Andrey Sharkov.”

    He added: 

    “I have indeed worked on some unique projects, but I don’t think my background is the most exciting subject for Wisconsin Rapids.”

    Industrial buildings, pipes and metal structures stand among trees next to a body of water, with power lines overhead.
    The site of a former paper mill in Wisconsin Rapids, Wis., is photographed from across the Wisconsin River on Aug. 12, 2026. The former paper mill site is the location of a proposed large-scale data center by industrial real estate development firm PNK Group. (Drake White-Bergey for Wisconsin Watch)

    City nearly poised to act?

    Mayor Zacher told Wisconsin Watch that perhaps 15 data center developers and another 15 manufacturers have explored the former mill site but most didn’t move forward. According to his understanding, most data center developers didn’t think enough electricity was available. 

    Zacher said he has tried to remain neutral as the current data center proposal has advanced and opposition has increased. The city must consider business proposals based on the project’s merits, not who makes them, he said.

    Voronkin’s group has continued to try to build local support, holding a series of four webinars in August.

    Zacher said the city is waiting for Voronkin’s group to provide more details on their proposal before it acts on their application for a conditional use permit and indicated the waiting time is limited.

    “I would say we don’t want to go months,” he said.

    Wisconsin Watch is a nonprofit, nonpartisan newsroom. Subscribe to our newsletters for original stories and our Friday news roundup.

    In Wisconsin Rapids, data center objections include developers’ Russian connections is a post from Wisconsin Watch, a non-profit investigative news site covering Wisconsin since 2009. Please consider making a contribution to support our journalism.

    Center connections data developers include objections Rapids Russian Wisconsin
    NCIJ NETWNCIJ NETWORK
    • Website

    Keep Reading

    Listen to 911 Calls From Inside an Immigration Detention Center — ProPublica

    Syracuse University Intervenes to Block Subpoena of Police Records — ProPublica

    Greens call for temporary ban on new data centres

    What the Data Says About AI in Security Operations in 2026

    More than 380 coastal World Heritage Sites may face climate risks, new data shows

    When agents act on their own, governance has to live in the data layer

    Add A Comment
    Leave A Reply Cancel Reply

    Editors Picks

    A Montana Community Rallies to Save Its Beloved Ski Hill

    August 28, 2026

    18-km pipeline installation and platform upgrades boost Gulf of Suez field

    August 28, 2026

    Listen to 911 Calls From Inside an Immigration Detention Center — ProPublica

    August 28, 2026

    In Wisconsin Rapids, data center objections include developers’ Russian connections

    August 28, 2026
    Latest Posts

    NASA’s Curiosity Discovers a Field of Martian Polygons

    July 29, 2026

    As crypto perpetual futures boom, Ethereum’s role is shifting

    July 29, 2026

    Critical Rails Flaw Could Let Unauthenticated Attackers Read Server Files via Image Uploads

    July 29, 2026

    Subscribe to News

    Get the latest sports news from NewsSite about world, sports and politics.

    NCIJ Network is an independent digital news platform delivering trusted investigative journalism, European and global news, in-depth analysis, and fact-based reporting with accuracy, transparency, and integrity.

    Facebook X (Twitter) Instagram Pinterest YouTube

    A Montana Community Rallies to Save Its Beloved Ski Hill

    August 28, 2026

    18-km pipeline installation and platform upgrades boost Gulf of Suez field

    August 28, 2026

    Listen to 911 Calls From Inside an Immigration Detention Center — ProPublica

    August 28, 2026

    Subscribe to Updates

    Get the latest creative news from FooBar about art, design and business.

    Type above and press Enter to search. Press Esc to cancel.