Close Menu
NCIJ Network NCIJ Network
    What's Hot

    How viable are plans to free up prison space in England and Wales? | Prisons and probation

    August 11, 2026

    A developer got Word 1.1a from 1990 to run on Windows 11 – try it yourself

    August 11, 2026

    Building and Validating a Quantitative Trading Strategy with OctoBot, Walk-Forward Backtesting, Parameter Optimization, and Interactive Analysis

    August 11, 2026
    Facebook X (Twitter) Instagram
    Trending
    • How viable are plans to free up prison space in England and Wales? | Prisons and probation
    • A developer got Word 1.1a from 1990 to run on Windows 11 – try it yourself
    • Building and Validating a Quantitative Trading Strategy with OctoBot, Walk-Forward Backtesting, Parameter Optimization, and Interactive Analysis
    • Windows 11 KB5121003 & KB5120240 cumulative updates released
    • Russia Approves Trading of Bitcoin, Ethereum and USDT—But No XRP
    • Quality of Thames Water ‘flagship’ chalk stream rated as poor
    • As Singapore culls ‘nuisance’ birds, rapid urbanization continues to fuel an avian boom
    • Trump Takes State Capitalism to New Levels
    • About
      • Our Team
      • Editorial Policy
      • Editorial Independence
      • International Support
    • Trust & Standards
      • AI Usage Policy
      • Conflict of Interest Policy
      • Corrections Policy
      • Ethics Policy
      • Fact-Checking Policy
      • Source Protection
    • Get Involved
      • Guide for Sources
      • Support Independent Journalism
    • Legal
      • Cookie Policy
      • Privacy Policy
      • Terms of Use
    Facebook X (Twitter) Instagram
    NCIJ Network NCIJ Network
    Tuesday, August 11
    • Home
    • World
    • Ai
    • Business
    • Politics
    • Health
    • Crypto
    • Science
    • Technology
    • Cybersecurity
    • Defense & Security
    • Economy
    • Energy
    • Europe
    • More
      • Fact Check
      • Investigations
      • Opinion & Analysis
      • Environment
    NCIJ Network NCIJ Network
    Home»Crypto & Blockchain

    Bitcoin Sales Fund Riot’s $9.1B AI Lease Before Rent Begins

    NCIJ NETWNCIJ NETWORKBy NCIJ NETWNCIJ NETWORKAugust 11, 2026 Crypto & Blockchain No Comments4 Mins Read
    Share
    Facebook Twitter LinkedIn Pinterest Email

    Bitcoin miner Riot Platforms has signed a 191-megawatt data center lease with an unnamed frontier AI lab that it expects to generate about $9.1 billion of gross contract revenue over a 20-year base term.

    Construction cash must arrive much sooner: the first 96 MW is expected to become available in December 2027, when initial rent is expected to commence, and the remaining 95 MW is due in June 2028. The plan still treats Bitcoin sales as a source of construction equity before rent begins.

    Riot projects $2.1 billion to $2.3 billion of capital spending for the build and assumes that 80% to 90% will come from long-term project debt. That debt is not disclosed as closed. The projected stack leaves $210 million to $460 million of equity funding before an expected $180 million refinancing tied to its AMD deployment would reduce the estimated equity need to $30 million to $280 million.

    Wall Street is paying up for Bitcoin miners’ AI infrastructure before most of it is built
    Related Reading

    Wall Street is paying up for Bitcoin miners’ AI infrastructure before most of it is built

    VanEck says AI-linked miners are earning premium valuations before most leased capacity is delivered, leaving execution, dilution, debt, and tenant quality as the next market test.

    Jun 17, 2026 · Gino Matos

    The first bridge is a $573 million interim facility administered by Morgan Stanley Senior Funding. It is intended for long-lead equipment and development costs, bears interest at SOFR plus 2.75% and matures on Oct. 15, 2026, subject to limited extension in specified refinancing circumstances. The filing does not say the entire facility was drawn or unconditionally available. Riot also says an investment-grade credit backstop is being finalized, without disclosing its provider, amount, conditions or completion.

    Infographic showing Riot Platforms’ projected AI build costs, Bitcoin treasury split and expected 2027–2028 rent timeline.Infographic showing Riot Platforms’ projected AI build costs, Bitcoin treasury split and expected 2027–2028 rent timeline.

    Bitcoin sales remain in the construction budget

    Riot’s presentation identifies continued Bitcoin sales from its inventory as the primary source for data center equity spending. No specific future sale is guaranteed, and Riot had not disclosed a post-quarter sale through Aug. 11, but management’s plan treats the treasury as a funding source.

    At June 30, Riot reported 11,380 Bitcoin, with 5,821 pledged against a fully drawn $200 million Coinbase Credit facility. That put 51.2% of its holdings under restriction, while 5,559 Bitcoin were not classified as restricted. Riot also sold 9,665 Bitcoin for $732.5 million during the first half of 2026.

    CryptoSlate Daily Brief

    Daily signals, zero noise.

    Market-moving headlines and context delivered every morning in one tight read.

    5-minute digest 100k+ readers

    Free. No spam. Unsubscribe any time.

    Whoops, looks like there was a problem. Please try again.

    You’re subscribed. Welcome aboard.

    Reported Riot 500 BTC custody transfer exposes Bitcoin miners' AI funding pressureReported Riot 500 BTC custody transfer exposes Bitcoin miners' AI funding pressure
    Related Reading

    Reported Riot 500 BTC custody transfer exposes Bitcoin miners’ AI funding pressure

    The transfer is not confirmed as a sale, but it points to a harder funding question for public miners.

    Jul 4, 2026 · Liam ‘Akiba’ Wright

    Its mining economics sharpen the treasury question without showing cash costs per coin above production value. Cost to mine one Bitcoin excluding miner depreciation was $49,912 in the second quarter, or 69.6% of the $71,667 production value. Including depreciation, the figure rose to $90,631, or 126.5% of production value.

    The including-depreciation measure was 26.5% above production value. But depreciation is a non-cash expense on mining hardware, not a variable cost that Riot can avoid by temporarily curtailing machines. The comparison therefore shows all-in accounting cost above production value, while Riot’s excluding-depreciation cost remained below it.

    Bitcoin’s broken production cost floor is splitting miners into survivors and sellersBitcoin’s broken production cost floor is splitting miners into survivors and sellers
    Related Reading

    Bitcoin’s broken production cost floor is splitting miners into survivors and sellers

    Bitcoin miners’ production cost was supposed to be the level Bitcoin couldn’t fall through, but it’s been sitting below it for weeks.

    Jun 27, 2026 · Andjela Radmilac

    The lease offers a large revenue path after capacity is delivered. Two extensions, each controlled by the tenant, could lift projected gross contract revenue to about $16.1 billion only if both are exercised. Until rent scales, Riot still needs financing that is not yet closed and continued Bitcoin sales for equity, leaving a near-term treasury trade-off inside its long-term AI strategy.

    9.1B begins Bitcoin Fund lease rent riots sales
    NCIJ NETWNCIJ NETWORK
    • Website

    Keep Reading

    Russia Approves Trading of Bitcoin, Ethereum and USDT—But No XRP

    OpenAI’s Only Dedicated Ethicist Has Left With No Replacement: FT

    Luke Dashjr Removed as BIP Editor After BIP-110 Bitcoin Fork Stalls

    TD Cowen Gives Crypto Clarity Act A 25% Chance Of Passing This Fall

    Bitcoin ETFs See Biggest Inflows Since April

    Coinbase Opens UK Derivatives Trading With Up to 50x Leverage

    Add A Comment
    Leave A Reply Cancel Reply

    Editors Picks

    How viable are plans to free up prison space in England and Wales? | Prisons and probation

    August 11, 2026

    A developer got Word 1.1a from 1990 to run on Windows 11 – try it yourself

    August 11, 2026

    Building and Validating a Quantitative Trading Strategy with OctoBot, Walk-Forward Backtesting, Parameter Optimization, and Interactive Analysis

    August 11, 2026

    Windows 11 KB5121003 & KB5120240 cumulative updates released

    August 11, 2026
    Latest Posts

    I grew up near Andy Burnham. This is what shaped our new PM | Andy Burnham

    July 25, 2026

    The Economic Philosophy of Britain’s Andy Burnham

    July 25, 2026

    Samsung Wallet Will Add Stablecoin Support, Including USDC

    July 25, 2026

    Subscribe to News

    Get the latest sports news from NewsSite about world, sports and politics.

    NCIJ Network is an independent digital news platform delivering trusted investigative journalism, European and global news, in-depth analysis, and fact-based reporting with accuracy, transparency, and integrity.

    Facebook X (Twitter) Instagram Pinterest YouTube

    How viable are plans to free up prison space in England and Wales? | Prisons and probation

    August 11, 2026

    A developer got Word 1.1a from 1990 to run on Windows 11 – try it yourself

    August 11, 2026

    Building and Validating a Quantitative Trading Strategy with OctoBot, Walk-Forward Backtesting, Parameter Optimization, and Interactive Analysis

    August 11, 2026

    Subscribe to Updates

    Get the latest creative news from FooBar about art, design and business.

    Type above and press Enter to search. Press Esc to cancel.